Schedule
Autor :
María Teresa Reyes Harfush
1.
It is the first step to create a schedule in a project
list
task
Make
of
a
2.
Is the last step in creating a schedule
the
schedule
Publish
3.
It aids in the planning, executing & control of the project work
to
a
schedule
The
create
reason
4.
Activities, in a Gantt chart are located in the
Vertical
Axis
5.
Time, in a Gantt chart, is located in the
Axis
Horizontal
6.
Duration, in a Gantt chart, are represente with
Horizontal
start
finish
date
date,
bars
with.